Before installation, the subfloor must be tested using a calibrated moisture meter or a concrete moisture test kit. For concrete slabs, the relative humidity (RH) test is common, often requiring levels below 75-80% depending on the specific flooring product. If moisture exceeds recommended limits, the installation must be delayed until a concrete sealer or vapor barrier is applied, preventing damage to the flooring's locking system or subfloor.